Published on: 18/09/2018 09:46 AMReported by: roving-eye
Transport leaders have announced a programme of platform upgrades designed to prepare the Merseyrail network for the arrival of the new, state of the art trains in 2020 that will transform how people travel.
The phased programme of upgrades will take place between 20 October 2018 and 16 June 2019. These vital works, delivered by Network Rail, will involve upgrading existing platforms and realigning track to ensure that they are compatible with the new trains and their ground breaking, sliding step technology that will provide unassisted access for all.
This means that wheelchair users can board the train without a ramp and passengers with prams and cycles can get on and off the train with ease. This technology represents a pioneering approach for the UK.
There will be 11 phases of works during this period. Only short sections of line will be closed at any one time, with all stations on that section closed. Closures will vary in duration, but most will be between nine and 30 days at a time.
High quality, rail replacement buses will get passengers to where they need to go as quickly as possible and some of these will be express services.
Merseytravel, Merseyrail and Network Rail have worked collaboratively on this project and significant planning work has been carried out to minimise the time needed to complete these important works and reduce disruption to passengers.
More detailed information will be made available in advance of each phase and travellers will be encouraged to plan ahead and consider their travel options including commercial buses and the Mersey Ferries.
Businesses and organisations are advised to think about what they may need to put in place to support staff and customers.
Key advice:
• You can still get to where you need to go
• Check before you travel. Closures are taking place at different locations at different times on the network so it’s important to keep checking what’s happening and when. Some timetables may change.
• Plan ahead – use journey planners and National Rail enquiries
• Leave more time for your journey. Timetables may change and your journey may be longer.
• Consider avoiding travelling at peak times where possible.
• Consider your options –including commercial buses and the Mersey Ferries.
For more information and further details about how your rail journeys will be affected visit www.merseyrail.org/itshappening
You may comment here but news always gets more discussion at our facebook.com/groups/southportnews
Useful links: Report Cyber Crime
| Stop Nuisance Calls & Mail
| Daily Covid Stats (updated 4pm)
| Covid excess deaths in your area
| Local NHS Resources
| What 3 Words
-
Member Post Likes / Dislikes - 0 Likes, 0 Dislikes
Check Todays Deals on Ebay.co.uk
Check Todays Deals On Amazon.co.uk
Your Comments:
-
Three weeks of 'High Quality' rail replacement 'Service' in February, ! week Southport - Hall Rd then 2 Weeks Formby to Bank Hall.
-
Member Post Likes / Dislikes - 0 Likes, 0 Dislikes
-
Ah so 4 weeks of longer journey times for which season ticket holders will get no compensation.
-
Member Post Likes / Dislikes - 0 Likes, 0 Dislikes